Protestors who spent nine nights in a bus shelter to save it from being bulldozed have been told their sit-in added £300,000 to the bill to replace it.

Norfolk County Council says last year’s stand-off in the seaside town of Sheringham has sent the price of a new travel hub soaring from £580,000 to £880,000.

The 1950s shelter on Station Approach, famed for its mural of a steam train passing through poppy fields, was due to be demolished last December.

But when the workmen arrived, locals moved in.

For nine days they camped out around the clock in freezing temperatures, arguing the shelter was part of the town’s heritage and that they had not been properly consulted.

Bailiffs turned up at 4am on the eighth day, only to be stood down hours later.

The following night the town council, which owns the land, voted 6-5 to save it.

The campaign drew global attention and was even addressed by then prime minister Sir Keir Starmer, who said on a visit to Norfolk that the county council should “listen and respond to local people”.

The victory did not last, however.

With buses unable to stop in the town centre, town councillors reversed their decision in June, and the shelter was flattened in July.

County Hall now says the months of delay pushed up the cost of labour and materials, while equipment already bought for the scheme had to be handed to other projects.

Tom Dickerson, the Reform UK cabinet member for highways and transport, told the BBC: “While I understand that people held strong views about the shelter, the additional costs and delays highlight the importance of residents and stakeholders engaging with us at the earliest opportunity helping to avoid unnecessary disruption and additional expense to the public.”

The extra cost will be covered by government bus grant funding.

But the council’s figures have been questioned by some.

Liz Withington, a Liberal Democrat councillor who joined the sit-in, told the BBC she was not “entirely convinced” the cost had risen by £300,000.

The scheme’s price tag had already climbed before the protest.

It was first budgeted at £350,000, then raised to £580,000 to pay for a bespoke shelter and other changes requested by residents.

Work on the travel hub is due to restart in January.