Harlequin Theatre closure may extend into 2028
Council aims for construction to start in November
The reopening of the Harlequin Theatre in Redhill may be delayed until "well into 2028," nearly five years after it was closed.
The theatre shuttered its doors in September 2023 due to safety fears linked to dangerous crumbly aerated concrete, which posed a collapse risk.
Reigate and Banstead Borough Council continues to investigate the extent of the structural issues, but campaigners have criticised the council for the slow progress.
The council, led by Councillor Richard Biggs, acknowledged frustrations and admitted that the situation could have been handled better.
He revealed that construction might begin as early as November 2026, subject to contract approval, and could take up to 15 months to complete.
The council has budgeted for the project, although contracts have not yet been signed.
Harlequin supporter David Fisher addressed a council meeting, expressing concern that permission from the head leaseholder was still pending.
Fisher urged the council leader for firm dates to help community groups plan future productions.
The council's leader acknowledged the project's delays were due to discovering additional issues during design work, necessitating comprehensive renovations.
The council aims to ensure the final theatre can serve the community for another 40 years, prioritising longevity and safety.
Councillor Richard Biggs expressed disappointment over the delays but emphasised the importance of getting the work right.
A confirmed reopening date can only be set once the theatre operator contract is signed, allowing for mobilisation and scheduling.
The council remains committed to ensuring the theatre's long-term future for community groups and the broader borough.