Major Tunstall Library and Baths regeneration plan cancelled
Plans for 39 flats end as council terminates agreement
Plans to turn Tunstall Library and Baths in Stoke-on-Trent into 39 flats have ended after the city council terminated its agreement with the developer.
Tunstall Library Developments Ltd had proposed bringing the historic buildings back into use, with a restaurant, gym and other facilities alongside the flats.
The council's planning committee refused the application in July over concerns about residential amenity and heritage harm, leaving the future of the project in doubt.
The council has now agreed to end the sale contract and funding agreement with the company, and to pay its final claim.
It has also agreed to buy the car park next to the buildings from the company's parent firm, Tunstall Library UK Ltd.
According to the council's decision notice, not buying the car park could leave a strip of land that blocks future plans for the site.
The project was allocated £3.5 million from the government's Levelling Up Fund in 2021.
After the refusal, the council said it would divert £1.6 million to the refurbishment of 10 buildings in Burslem.
The remaining £1.9 million has gone towards a substation in Greengate Street, the car park purchase and outstanding project claims.
The decision notice says the company is unlikely to get planning permission, so the agreement had to end to avoid handing the money back to government.
All Levelling Up funding has to be spent by March 2028.