£4m railway investment in North West aims to minimise holiday travel disruption
Crewe and Preston among key hubs benefiting from upgrades during festive period.
Network Rail is investing over £4 million in the North West this Christmas with numerous upgrades planned to minimise disruption to travelers.
The bulk of work will take place on Christmas Day and Boxing Day, a period when trains traditionally do not run.
In Crewe, £1 million will be invested in platform modifications ahead of significant roof removals scheduled for May 2027.
Drainage systems will also be diverted in preparation for track renewals next February.
Additionally, work near Crewe at Weaver Junction will involve laying cables, clearing vegetation, and positioning materials for future power supply and signaling upgrades, forming part of a planned £200 million investment in upgrading this key transport hub.
In Lancashire, Preston and Warrington will see £1 million dedicated to overhead power line improvements.
Chester will benefit from signaling upgrades extending towards Hooton and Sandycroft as part of a wider £7 million area investment.
The electrification of new sidings at Brewery Junction in East Manchester and £1.7 million in track upgrades at Longsight, including the renewal of 2.5 km of railway en route to Manchester Piccadilly station, will further ensure the reliability of passenger and freight journeys for years to come.
Chris Wright, Network Rail’s North West route director, emphasized the importance of the investment saying it would make the railway more resilient and reliable, while helping prepare the network for major improvements planned next year.
While disruption will be minimized by scheduling most works for Christmas Day and Boxing Day, those traveling on transpennine routes and to the Midlands should check travel details and allow extra time.
Most railways will remain open throughout the festive season, ensuring passengers can travel to spend time with friends and family.