Plaque marks Botley Road closure as traders describe lingering anger

Business owners say the impact is still being felt after the road reopened

The plaque on First Stop Spanner Works, Ferry Hinksey Road
Author: Jecs DaviesPublished 28th Oct 2026

A blue plaque has been installed on a garage near Botley Road in protest at the disruption caused by its closure.

The road reopened on 20th September after three and a half years and repeated delays, with a new £237.4 million rail bridge in place.

The bridge has drawn criticism, including over its cost, the time it took to build and its appearance.

Traders said they lost custom and footfall during the closure and not every business survived, with Courtney Pianos citing the works as a key cause of its closure.

The plaque

Zack Iqbal runs First Stop Spanner Works on Ferry Hinksey Road and fitted the sign to his garage to commemorate what his business went through.

The plaque reads: 'to commemorate the three years of chaos (2023-2026) and £millions wasted by Network Rail and Keir in trying to build a bridge'.

Mr Iqbal said: "After three and a half long years of unprecedented disruption, I am incredibly relieved to welcome my customers back now that the Botley Road bridge has finally reopened.

"The road closure since April 2023 was a massive ordeal for independent local businesses."

He added: "Throughout it all, I felt deeply let down and ignored by the large institutions, including Oxford City Council and Oxfordshire County Council, who treated our livelihoods with disdain while the project suffered endless delays.

"The sign on my garage simply reflects my immense frustration with how this situation was handled."

'Total worldwide embarrassment'

Tom Rainey runs the Punter on Osney Island and does not feel the plaque represents the loss he experienced during the closure.

He is concerned the issue is being trivialised and estimates his business was affected to the tune of £1 million.

Mr Rainey said he had no expectation that his business or others would be supported following the reopening.

He said: "I would not expect Oxford City Council to help any business and it will take years for us to re-establish the business to where it was four years ago.

"Anger is still the only word I can use to sum up this total worldwide embarrassment."

MP calls for accountability

Liberal Democrat MP Layla Moran has said scrutiny of the project must continue after the reopening.

In a letter sent to people living on Botley Road, she described the reopening as a moment of relief but said many people had lost faith in the project.

Ms Moran wrote: "I want accountability for this project, and I want to ensure that lessons are learned from this project."

She said she had spent years pressing Network Rail and government ministers over the impact on people living nearby and on traders.

Last year, £850,000 in goodwill payments was distributed to some local businesses after sustained pressure from campaigners, councillors and MPs.

Network Rail, Oxfordshire County Council and Oxford City Council were contacted for comment.