Music vibrations blamed as possible factor in Bristol bridge collapse
A council report also reveals love locks prevented safety test lifts for almost a decade, with corrosion and damage found during later inspections
Vibrations from music played near Bristol's harbourside could have played a part in the latest collapse of Pero's Bridge, according to the chair of the city council's harbour committee.
Councillor Andrew Brown said engineers felt vibrations on the bridge from music being played on the shore, next to the bars and lounges, during a routine inspection the night before the bridge's central span partially entered the harbour on 31st October.
He said: "We think that there could have been external vibrations that could have dislodged the bridge from the position it had been in, which as you may recall, was quite precarious."
Brown said the cause is far from certain.
He said: "It's really difficult to pin down any one potential explanation, but that is a potential explanation for the further slippage that happened."
A Bristol City Council report says engineering assessments indicate external vibration was the most likely contributory factor to the 31st October movement.
It says the source of the vibration has not yet been identified, but that wind is unlikely.
Years without proper testing
The same report says the bridge could not be properly tested for almost a decade before it collapsed, because of the weight of the love locks attached to it.
It says test lifts were carried out every three months to check the mechanism was reliable, until 2016, when the weight of the padlocks made this impossible.
The bridge was built in 1999.
About three tonnes of locks were removed in August 2025, ahead of a planned £1.51m refurbishment.
The report says inspections in 2025 and 2026 identified corrosion, water damage and deterioration to the bridge's bearings and hydraulic lifting system.
On 13th August, the bridge was raised for a planned engineering inspection and test.
The report says that during the lowering process it suddenly accelerated and became displaced from its normal operating position.
It says the exact cause of the collapse is still under investigation, but preliminary engineering assessments point towards a possible failure within the hydraulic lifting system.
Impact on harbourside businesses
Brown said businesses on the pedestrian route between Queen Square, Anchor Square and Millennium Square could be affected while the bridge is out of action.
He said: "I think the challenges for passing trade, particularly on the pedestrian route from Queen Square through to Anchor Square and Millennium Square, that's, you know, businesses in that area might lose some of the trade that they would previously get as people divert to go round the top of St Augustine's Reach."
Brown said the issue was a challenge for the council as well as for businesses.
He said: "That's the real, the real challenge for them and for us as a city, and you know, finding ways to try and manage that and direct people to those parts of the harbour side that are just slightly more difficult to get to than they were."
What happens next
The council is preparing a specialist recovery operation, estimated to cost around £280,000, to remove the bridge spans and take them to Albion Dry Dock.
It says the cost is already covered by the approved £1.51m budget for the project, and it does not expect a significant increase.
The council hopes repairs and reinstatement will be finished before the summer, although this depends on what engineers find once the bridge has been recovered.
Brown said the council has been working with the bridge's original designers on how to make it more robust.
He said: "And, you know, now we've not got the locks on it anymore, we'll be able to return to sort of regular programme of maintenance and regular lifting."
What happens to the love locks
Brown said the locks removed from the bridge have been kept.
He said: "So the locks, we took the locks off last year. We still have locks, so that's an ambition to make some sort of public artwork out of them. But we need to find funding to do that."